A can do a peice of work in 10 days B can do work in 15 days .In how many days will they get do the work together.​

Question

A can do a peice of work in 10 days B can do work in 15 days .In how many days will they get do the work together.​

in progress 0
Madelyn 2 months 2021-11-10T16:45:44+00:00 2 Answers 0 views 0

Answers ( )

    0
    2021-11-10T16:47:17+00:00

    Answer:

    6 days

    Step-by-step explanation:

    Work done by A in 1 day = 1/10

    Work done by B in 1 day = 1/15

    Work done by A and B together in 1 day = 1/10 + 1/15 = 5/30 = 1/6

    Therefore, A and B will complete the work together in [ 1 ÷ (1/6) ] days = 6 days

    0
    2021-11-10T16:47:33+00:00

    Answer:

    A can do a piece of work in 10 days.

    A can do 1/10 part of a piece of work in 1 day.

    B can do a piece of work in 15 days.

    B can do 1/15 part of a piece of work in 1 day.

    A and B together can do (1/10 + 1/15)  part of a piece of work in 1 day

    = 1/6

    A and B together can do a piece of work in 1/1/6 days

    = 6 days

    therefore,  A and B will get 6 days to do the work

    Step-by-step explanation: