12. A and B can finish a piece of work in 6 days and 4 days, respectively, working alone. A started the work. After 2 days, he was join

Question

12. A and B can finish a piece of work in 6 days and 4 days, respectively, working alone.
A started the work. After 2 days, he was joined by B. Find the time taken to finish the
remaining work.

in progress 0
Melody 2 months 2021-12-03T03:51:35+00:00 2 Answers 0 views 0

Answers ( )

    0
    2021-12-03T03:53:03+00:00

    Answer:

    05

    I think this is the right answer

    BRAINLIEST

    0
    2021-12-03T03:53:30+00:00

    Answer:

    given,

    A and B can finish a piece of work in 6 & 4 days respectively.

    that means,

    A’s one day work is 1/6,

    B’s one day work is 1/4.

    A started the work and do alone for 2 days,

    that means he complete 2/6=1/3 of total work.

    then, A and B do the work together,let it be X days to complete the remaining 2/3 work,

    therefore,X/6+X/4 = 2/3,

    =>5X/12 = 2/3,

    =>X=8/5=1(3/5)days,

    therefore,the time taken to finish remaining work is 1(3/5)days.

    Hope it helps u…